| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20056127 | Name of Scheme: Sundaripur PWS | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 2100 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 22-Sep-2023 | Actual Date of Completion (Capex): 15-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well | 30.12 Mtr./138.54 Mtr. | Sundaripur | 26.472165 | 79.568355 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | (32.8 M3/Hr)/53Mtr. | Sundaripur | 26.472165 | 79.568355 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 150/16 | Sundaripur | 26.472977 | 79.578887 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I. | 100 | .01 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5.07 | |
| 2 | HDPE | 75 | .23 | |
| 3 | HDPE | 90 | .88 | |
| 4 | HDPE | 140 | 4.32 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 473 |