Project Completion Certificate (Ground Water)
Scheme ID: 20056373 Name of Scheme: Jhal Village Water Supply Scheme Reorganisation No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3788 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 21-Dec-2023 Actual Date of Completion (Capex): 09-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 200 mm plain pipe 64.55 mtr plain pipe new oht campus 29.408011529796646, 77.33960863356033
2 200 mm slotted pipe 30 mtr slotted pipe new oht campus 29.408011529796646, 77.33960863356033
3 300 mm plain pipe 60 mtr plain pipe new oht campus 29.408011529796646, 77.33960863356033
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 solar pump 20 HP 750 m3/ 53 mtr head new oht campus 29.408011529796646, 77.33960863356033
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 concrete oht 200 kl/ 16 mtr new oht campus 29.408011529796646, 77.33960863356033
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K9 150 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 7.636
2 HDPE 75 0.064
3 HDPE 90 0.385
4 HDPE 125 0.447
5 HDPE 140 0.682
6 HDPE 160 0.036
HSC Connection
Sno. Total Nos.
1 670
Other Details
245.32
223.62
223.62