| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20056373 | Name of Scheme: Jhal Village Water Supply Scheme Reorganisation | No. of Villages: 1 | No. of Habitation Covered: 1 |
| Total Population Covered: 3788 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 21-Dec-2023 | Actual Date of Completion (Capex): 09-Nov-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 200 mm plain pipe | 64.55 mtr plain pipe | new oht campus | 29.408011529796646, | 77.33960863356033 |
| 2 | 200 mm slotted pipe | 30 mtr slotted pipe | new oht campus | 29.408011529796646, | 77.33960863356033 |
| 3 | 300 mm plain pipe | 60 mtr plain pipe | new oht campus | 29.408011529796646, | 77.33960863356033 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | solar pump 20 HP | 750 m3/ 53 mtr head | new oht campus | 29.408011529796646, | 77.33960863356033 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | concrete oht | 200 kl/ 16 mtr | new oht campus | 29.408011529796646, | 77.33960863356033 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K9 | 150 | 0.03 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 7.636 | |
| 2 | HDPE | 75 | 0.064 | |
| 3 | HDPE | 90 | 0.385 | |
| 4 | HDPE | 125 | 0.447 | |
| 5 | HDPE | 140 | 0.682 | |
| 6 | HDPE | 160 | 0.036 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 670 |