Project Completion Certificate (Ground Water)
Scheme ID: 20058132 Name of Scheme: MIRKAPUR (GOGP) JJM No. of Villages: 7 No. of Habitation Covered: 9
Total Population Covered: 7940 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 14-Nov-2024 Actual Date of Completion (Capex): 28-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 29M/121M MIRKAPUR 27.363876 79.918396
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 89.4M³/47M MIRKAPUR 27.363876 79.918396
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 450KL/18M MIRKAPUR 27.363876 79.918396
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 200 0.032
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN:-6 63 9.587
2 HDPE PIPE PN:-6 75 7.756
3 HDPE PIPE PN:-6 90 3.693
4 HDPE PIPE PN:-6 110 0.804
5 HDPE PIPE PN:-6 125 0.552
6 HDPE PIPE PN:-6 140 0.00
7 HDPE PIPE PN:-6 160 0.613
8 HDPE PIPE PN:-6 180 0.00
9 HDPE PIPE PN:-6 200 2.925
HSC Connection
Sno. Total Nos.
1 1945
Other Details
4.27
0.00
4.67
27-Jun-2025
25-Sep-2025