Scheme ID: 20058444 Name of Scheme: REHADRA & MURADGAON URF KUWAKHEDA No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2720 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 25-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 33.14 MTr / 89.84 Mtr REHDRA MURADGAON URF KUAN KHERA 28.935158 77.916346
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 550 LPM / 54 Mtr REHDRA MURADGAON URF KUAN KHERA 28.935158 77.916346
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175KL / 16M REHDRA MURADGAON URF KUAN KHERA 28.935158 77.916346
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.02295
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.716
2 HDPE 90 1.214
3 HDPE 110 0.686
4 HDPE 125 0.216
5 HDPE 140 0.168
HSC Connection
Sno. Total Nos.
1 456
Other Details
2.71
2.71
2.15
10-Aug-2024
02-Mar-2025