Project Completion Certificate (Ground Water)
Scheme ID: 20058471 Name of Scheme: JANDHERI & KHERI JADID No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 4709 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 25-Aug-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 37.19 Mtr / 100.07 Mtr KHERKI ZADID 29.062618 77.893217
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 900 LPM / 54 Mtr KHERKI ZADID 29.062618 77.893217
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250 Kl / 16 M KHERKI ZADID 29.062618 77.893217
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0178 Laying Work done in Kherki Zadid Only
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.994 This is a multi-village scheme comprising two villages, Kherki Zadid & Jantheri. The work has been completed in Kherki Zadid, but in Jantheri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
2 HDPE 90 1.501 This is a multi-village scheme comprising two villages, Kherki Zadid & Jantheri. The work has been completed in Kherki Zadid, but in Jantheri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
3 HDPE 160 0.0324 This is a multi-village scheme comprising two villages, Kherki Zadid & Jantheri. The work has been completed in Kherki Zadid, but in Jantheri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
4 HDPE 180 0.292 This is a multi-village scheme comprising two villages, Kherki Zadid & Jantheri. The work has been completed in Kherki Zadid, but in Jantheri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
5 HDPE 200 0.264 This is a multi-village scheme comprising two villages, Kherki Zadid & Jantheri. The work has been completed in Kherki Zadid, but in Jantheri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
HSC Connection
Sno. Total Nos.
Other Details
4.09
4.09
2.59
11-Jan-2025
12-Jan-2025