Project Completion Certificate (Ground Water)
Scheme ID: 20058530 Name of Scheme: PHOOLPUR Water Supply Scheme No. of Villages: 1 No. of Habitation Covered: 7
Total Population Covered: 2600 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 26-Dec-2023 Actual Date of Completion (Capex): 27-Feb-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of Tubewell Assembly 21.20/137.44 Phoolpur 26.599091 82.506293
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Ac Submersible Pump 550 Phoolpur 26.599091 82.506293
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 rcc 150/14 Phoolpur 26.599091 82.506293
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 150 0.036
2 DI-K7 200 0.026
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 1.572
2 HDPE Pipe PN-6: Class PE-100 75 1.358
3 HDPE Pipe PN-6: Class PE-100 63 9.321
4 HDPE Pipe PN-6: Class PE-100 125 0.923
5 HDPE Pipe PN-6: Class PE-100 140 0.162
6 HDPE Pipe PN-6: Class PE-100 180 0.875
HSC Connection
Sno. Total Nos.
1 331
Other Details
2.19
2.19
2.23
02-Jun-2025
03-Jun-2025