Project Completion Certificate (Ground Water)
Scheme ID: 20058888 Name of Scheme: AITHER & KHAIRI WSS No. of Villages: 4 No. of Habitation Covered: 9
Total Population Covered: 3050 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 19-Mar-2024 Actual Date of Completion (Capex): 10-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24.00/107.30 AITHER 26.831246 81.753978
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT PUMP 608LPM/45Mtr AITHER 26.831246 81.753978
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/16 AITHER 26.831215 81.753758
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI K-7 125 0.0258
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 200 0.3338
2 HDPE Pipe PN-6: Class PE-100 180 0.2481
3 HDPE Pipe PN-6: Class PE-100 160 0.4884
4 HDPE Pipe PN-6: Class PE-100 140 0.9826
5 HDPE Pipe PN-6: Class PE-100 125 1.1961
6 HDPE Pipe PN-6: Class PE-100 110 1.6817
7 HDPE Pipe PN-6: Class PE-100 90 0.0000
8 HDPE Pipe PN-6: Class PE-100 75 0.8898
9 HDPE Pipe PN-6: Class PE-100 63 8.9003
HSC Connection
Sno. Total Nos.
1 520
Other Details
2.52
0.00
3.04
10-Jun-2024
01-Feb-2025