Project Completion Certificate (Ground Water)
Scheme ID: 20064085 Name of Scheme: Ashrafabad WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 4
Total Population Covered: 1410 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 16-Sep-2024 Actual Date of Completion (Capex): 21-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 16 (m) / 80 (m) Ashrafabad 26.369131 81.320182
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 440 (Mtr.) Ashrafabad 26.369131 81.320182
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Elevated Storage Reservoir 150 (KL) / 16 (Mtr.) Ashrafabad 26.369131 81.320182
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K9 150 0.009
2 DI-K9 100 0.012
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.839
2 HDPE 75 1.459
3 HDPE 90 1.277
4 HDPE 110 0.487
5 HDPE 125 0.382
6 HDPE 140 0.302
HSC Connection
Sno. Total Nos.
1 344
Other Details
2.22
0.00
2.15
23-Jun-2024
21-Nov-2024