Project Completion Certificate (Ground Water)
Scheme ID: 20064779 Name of Scheme: Suwah Gram Panchayat Water Supply Scheme No. of Villages: 2 No. of Habitation Covered: 3
Total Population Covered: 1940 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 29-Jun-2024 Actual Date of Completion (Capex): 02-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Depth of Strainer (m) 18.05 TW 26.183775 83.698933
2 Depth of Plain Pipe (m) 101.33 TW 26.183775 83.698933
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible pump 450/42 TW 26.183775 83.698933
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Zinc Tank 125/14 OHT 26.183769 83.698936
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI k7 100 0.03
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN6 PE100 63 9.17
2 HDPE PN6 PE100 75 0.789
3 HDPE PN6 PE100 90 1.0
4 HDPE PN6 PE100 140 1.1
HSC Connection
Sno. Total Nos.
1 296
Other Details
1.79
1.67
0.00
01-Apr-2025
02-Apr-2025