Project Completion Certificate (Ground Water)
Scheme ID: 20065072 Name of Scheme: BHARAMAU No. of Villages: 3 No. of Habitation Covered: 6
Total Population Covered: 2699 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 18-Jan-2024 Actual Date of Completion (Capex): 01-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 18/104.38 BHARAMAU 26.661953 79.729811
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 600/60 BHARAMAU 26.661953 79.729811
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/14 BHARAMAU 26.661953 79.729811
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/K7 100 0.098
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.308
2 HDPE 90 3.556
3 HDPE 110 1.054
4 HDPE 140 1.233
5 HDPE 160 0.426
HSC Connection
Sno. Total Nos.
1 506
Other Details
3.06
0.00
2.51
10-Apr-2024
11-Apr-2024