Project Completion Certificate (Ground Water)
Scheme ID: 20065165 Name of Scheme: KAPURIPUR Water Supply Scheme No. of Villages: 2 No. of Habitation Covered: 8
Total Population Covered: 2387 Base Year: 2022 Intermediate Year: 2038 Design Year: 2052
Date of Completion (As per Contract): 17-Feb-2024 Actual Date of Completion (Capex): 07-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 14.02 / 57.50 Kapuripur 81.57679379 26.41755616
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Pump 500 LPM/ 54 M kapuripur 81.57679379 26.41755616
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 150 kl / 16 MTR kapuripur 81.57692924 26.41766513
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI- k7 100 0.236
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PN-6 63 6.36
2 HDPE PN-6 90 1.02
3 HDPE PN-6 110 1.62
4 HDPE PN-6 140 0.60
5 HDPE PN-6 160 0.4
HSC Connection
Sno. Total Nos.
1 484
Other Details
2.19
0.00
2.21
10-Aug-2024
13-Nov-2024