Project Completion Certificate (Ground Water)
Scheme ID: 20065249 Name of Scheme: Kalla No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2700 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 23-Sep-2022 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube well 24/162.46 Kalla 26.239773 79.809439
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 64.54/67 Kalla 26.239773 79.809439
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/12 Kalla 26.239773 79.809439
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.020 As per Site
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 2.693 As per Site
2 HDPE 75 0.094 As per Site
3 HDPE 90 0.164 As per Site
4 HDPE 110 0.250 As per Site
5 HDPE 125 1.009 As per Site
6 HDPE 140 0.269 As per Site
HSC Connection
Sno. Total Nos.
1 340
Other Details
1.72
1.85
1.85
31-Mar-2023
01-Apr-2023