| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20065634 | Name of Scheme: Chanpur kakraiya PWS | No. of Villages: 1 | No. of Habitation Covered: 5 |
| Total Population Covered: 4454 | Base Year: 2023 | Intermediate Year: 0 | Design Year: 0 |
| Date of Completion (As per Contract): 01-Jun-2022 | Actual Date of Completion (Capex): 08-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube Well | 34.98 m / 135.34 m | Chandpur | 26.58677 | 79.380899 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 900 Lpm / 51 m | Chandpur | 26.58677 | 79.380899 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Oht | 250 kl / 14 m | Chandpur | 26.58677 | 79.380899 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | D.I | 150 | 0.0146 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 4.5156 | |
| 2 | HDPE | 90 | 3.4649 | |
| 3 | HDPE | 110 | 0.2718 | |
| 4 | HDPE | 140 | 0.5285 | |
| 5 | HDPE | 180 | 2.9675 | |
| 6 | HDPE | 200 | 2.1535 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 942 |