Project Completion Certificate (Ground Water)
Scheme ID: 20065721 Name of Scheme: BADAGAON WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 4132 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 09-Jan-2023 Actual Date of Completion (Capex): 04-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 19 m/ 51.60 m BADAGAON 26.067749 81.803095
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 870 LPM / 56 M BADAGAON 26.067749 81.803095
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250KL / 18 M BADAGAON 26.067749 81.803095
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0229
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.326
2 HDPE 90 4.444
3 HDPE 110 0.769
4 HDPE 125 0.275
5 HDPE 140 0.275
6 HDPE0.425 160 0.425
7 HDPE 180 1.037
HSC Connection
Sno. Total Nos.
1 672
Other Details
3.91
0.00
3.86
04-Sep-2024
05-Dec-2024