Project Completion Certificate (Ground Water)
Scheme ID: 20065961 Name of Scheme: BISRA PURAB WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 13
Total Population Covered: 3811 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 05-Aug-2024 Actual Date of Completion (Capex): 10-Jun-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 MS PIPE (300MM) 15 M/42.5 M BISARA PURAB 26.347746 81.790582
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 850 LPM/54 M BISARA PURAB 26.347746 81.790582
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 225KL / 16M BISARA PURAB 26.347746 81.790582
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 0.0328
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE (63MM-160MM) 160 17.342
HSC Connection
Sno. Total Nos.
1 795
Other Details
3.95
0.00
3.93
11-Sep-2025
23-Dec-2025