| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20066220 | Name of Scheme: Jamurwa Water Supply Scheme | No. of Villages: 2 | No. of Habitation Covered: 6 |
| Total Population Covered: 1513 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 22-Sep-2024 | Actual Date of Completion (Capex): 30-Jun-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 20(m) / 219.3(m) | Jamurwa | 26.436516 | 81.252604 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump | 370(M³) / 45(Mtr.) | Jamurwa | 26.436516 | 81.252604 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Elevated Storage Reservoir | 100 (KL) / 12(Mtr.) | Jamurwa | 26.436516 | 81.252604 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI-K9 | 150 | 0.020 | |
| 2 | DI-K9 | 100 | 0.006 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 2.184 | |
| 2 | HDPE | 75 | 1.777 | |
| 3 | HDPE | 90 | 2.005 | |
| 4 | HDPE | 110 | 0.478 | |
| 5 | HDPE | 125 | 0.401 | |
| 6 | HDPE | 160 | 0.251 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 250 |