Project Completion Certificate (Ground Water)
Scheme ID: 20066405 Name of Scheme: Newada water supply scheme No. of Villages: 2 No. of Habitation Covered: 5
Total Population Covered: 3315 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 04-Aug-2024 Actual Date of Completion (Capex): 22-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 20/96.3 NEWADA 26.157866 83.117817
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 450/45 NEWADA 26.157866 83.117817
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150/12 NEWADA 26.157866 83.117817
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 K-7/DI PIPE 200 0.05
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 8.372
2 HDPE Pipe PN-6: Class PE-100 75 0.3
3 HDPE Pipe PN-6: Class PE-100 125 0.734
4 HDPE Pipe PN-6: Class PE-100 140 0.131
HSC Connection
Sno. Total Nos.
1 330
Other Details
2.10
2.10
2.08
22-Oct-2024
23-Oct-2024