| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20066523 | Name of Scheme: ARIFPUR & SARAI BHAMAL GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 2 | No. of Habitation Covered: 3 |
| Total Population Covered: 3135 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 16-Aug-2024 | Actual Date of Completion (Capex): 10-Nov-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 16/103.52 | ARIFPUR & SARAI BHAMAL | 79.42368 | 27.04581 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump-1 | 700 LPM/65 M | ARIFPUR & SARAI BHAMAL | 79.42368 | 27.04581 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 200 KL/ 18 M | ARIFPUR & SARAI BHAMAL | 79.42368 | 27.04581 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.019 | Rising main |
| 2 | DI | 200 | 0.0080 | Rising main |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 1.65 | Distribution |
| 2 | HDPE | 63 | 4.62 | Distribution |
| 3 | HDPE | 110 | 2.298 | Distribution |
| 4 | HDPE | 160 | 1.196 | Distribution |
| 5 | HDPE | 180 | 2.003 | Distribution |
| 6 | HDPE | 200 | 1.38 | Distribution |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 567 |