Project Completion Certificate (Ground Water)
Scheme ID: 20066570 Name of Scheme: ITAURI & BHAIRO PUR VILLAGE WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 9
Total Population Covered: 4319 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Dec-2023 Actual Date of Completion (Capex): 11-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 17/215.34 ITAURI & BHAIRO PUR 26.423831 81.620023
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 900LPM/ 54 M ITAURI & BHAIRO PUR 26.423831 81.620023
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250 KL / 16 M ITAURI & BHAIRO PUR 26.423831 81.620023
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.028
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 8.813
2 HDPE 90 4.861
3 HDPE 110 1.367
4 HDPE 125 1.243
5 HDPE 140 0.831 `
6 HDPE 160 0.634
7 HDPE 180 0.188
HSC Connection
Sno. Total Nos.
1 524
Other Details
4.85
0.00
4.83
11-Sep-2024
13-Dec-2024