| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20066583 | Name of Scheme: KAMOLIYA & PIKOURA GROUP OF GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 3 | No. of Habitation Covered: 8 |
| Total Population Covered: 5060 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 12-Jan-2024 | Actual Date of Completion (Capex): 31-Dec-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 38.81M/185.64M | Kamoliya & Pikoura | 26.278384 | 81.935984 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible Pump- 1 & 2 | 530 LPM/ 50 M | Kamoliya & Pikoura | 26.278384 | 81.935984 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 300 KL/ 16 M | Kamoliya & Pikoura | 26.278384 | 81.935984 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI/ K7 | 100 | 0.35 | |
| 2 | DI/ K7 | 125 | 0.430 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE/ PN-6:Class PE-100 | 63 | 16.248 | |
| 2 | HDPE/ PN-6:Class PE-100 | 75 | 2.194 | |
| 3 | HDPE/ PN-6:Class PE-100 | 90 | 0.819 | |
| 4 | HDPE/ PN-6:Class PE-100 | 110 | 1.26 | |
| 5 | HDPE/ PN-6:Class PE-100 | 125 | 0 | |
| 6 | HDPE/ PN-6:Class PE-100 | 140 | 0.1 | |
| 7 | HDPE/ PN-6:Class PE-100 | 160 | 0 | |
| 8 | HDPE/ PN-6:Class PE-100 | 180 | 2.605 | |
| 9 | HDPE/ PN-6:Class PE-100 | 200 | 1.668 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 873 |