Project Completion Certificate (Ground Water)
Scheme ID: 20066658 Name of Scheme: KHOKHIPUR & BUKUNPUR GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 9
Total Population Covered: 10050 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 18-Jul-2024 Actual Date of Completion (Capex): 01-Mar-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 72.00 M / 286.0 M KHOKHIPUR & BUKUNPUR 26.303049 81.895406
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 665 LPM / 50 M KHOKHIPUR & BUKUNPUR 26.303049 81.895406
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 400 KL / 18 M KHOKHIPUR & BUKUNPUR 26.303049 81.895406
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI /K7 125 1.145
2 DI /K7 200 1.298
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE / PN-6: Class PE-100 63 22.93
2 HDPE / PN-6: Class PE-100 75 3.308
3 HDPE / PN-6: Class PE-100 90 1.517
4 HDPE / PN-6: Class PE-100 110 2.173
5 HDPE / PN-6: Class PE-100 125 0.648
6 HDPE / PN-6: Class PE-100 160 1.944
7 HDPE / PN-6: Class PE-100 180 0.391
HSC Connection
Sno. Total Nos.
1 1002
Other Details
5.82
0.00
5.95
02-Jun-2025
01-Aug-2025