Project Completion Certificate (Ground Water)
Scheme ID: 20066787 Name of Scheme: TATINA No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2444 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 20-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 28.96 Mtr / 93.06 Mtr TATINA 29.057866 77.908134
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 200 LPM / 48 Mtr TATINA 29.057866 77.908134
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 75 Kl / 12 M TATINA 29.057866 77.908134
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.019
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 3.200
2 HDPE 90 1.557
3 HDPE 110 0.209
4 HDPE 140 0.478
HSC Connection
Sno. Total Nos.
1 587
Other Details
2.17
2.17
1.75
06-Nov-2024
21-Jan-2025