Scheme ID: 20066869 Name of Scheme: Alipur Gram Panchayat Water Supply Scheme No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 3983 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 10-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Plain Pipe - 300 mm dia 51.54 Alipur 25.955380 81.524852
2 Slotted Pipe - 300 mm dia 11 Alipur 25.955380 81.524852
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 12.5 HP 27/47 Alipur 25.955380 81.524852
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Precast 150/12 Alipur 25.955380 81.524852
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.030
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 10.135
2 HDPE 75 0.272
3 HDPE 90 0.804
4 HDPE 110 0.548
5 HDPE 125 0.504
6 HDPE 140 0.258
HSC Connection
Sno. Total Nos.
1 335
Other Details
1.98
1.97
1.94
27-Dec-2024
28-Dec-2024