Project Completion Certificate (Ground Water)
Scheme ID: 20066919 Name of Scheme: PADRE & KANEHATI GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 19
Total Population Covered: 5320 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 12-Jan-2024 Actual Date of Completion (Capex): 31-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 39.03M/ 189.26M Padre & Kanehati 26.479373 81.975966
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump- 1 & 2 560LPM/ 48 M & 560LPM/ 53M Padre & Kanehati 26.479373 81.975966
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 325 KL/ 16 M Padre & Kanehati 26.479373 81.975966
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI/ K7 125 1.175
2 DI/ K7 250 0.095
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE/ PN-6: Class PE-100 63 17.857
2 HDPE/ PN-6: Class PE-100 75 4.031
3 HDPE/ PN-6: Class PE-100 90 2.351
4 HDPE/ PN-6: Class PE-100 110 1.264
5 HDPE/ PN-6: Class PE-100 125 0.066
6 HDPE/ PN-6: Class PE-100 140 0.35
7 HDPE/ PN-6: Class PE-100 160 1.203
8 HDPE/ PN-6: Class PE-100 180 0.224
9 HDPE/ PN-6: Class PE-100 200 1.194
HSC Connection
Sno. Total Nos.
1 909
Other Details
4.86
0.00
4.96
30-Jan-2025
01-Feb-2025