Project Completion Certificate (Ground Water)
Scheme ID: 20067284 Name of Scheme: SARAI THEKU GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 4
Total Population Covered: 2658 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 16-Aug-2024 Actual Date of Completion (Capex): 22-Apr-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 52.02/100.00 SARAI THEKU 79.5808877 27.0414045
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump-1 600 LPM/61 M SARAI THEKU 79.5808877 27.0414045
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 150 KL/ 14 M SARAI THEKU 79.5808877 27.0414045
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.029 Rising main
2 DI 150 0.010 Rising main
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.635 Distribution
2 HDPE 63 4.707 Distribution
3 HDPE 110 0.88 Distribution
4 HDPE 140 1.16 Distribution
HSC Connection
Sno. Total Nos.
1 496
Other Details
2.53
2.51
2.53
26-Jul-2024
27-Jul-2024