| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20067620 | Name of Scheme: JEWAN GRAM PANCHAYAT WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 5 |
| Total Population Covered: 3885 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 16-Aug-2024 | Actual Date of Completion (Capex): 30-Apr-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 28.00/147.32 | JEWAN | 27.06936 | 79.82786 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSSIBLE PUMP | 850/71 | JEWAN | 27.06936 | 79.82786 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 250/14 | JEWAN | 27.06936 | 79.82786 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.0115 | RISING MAINS |
| 2 | DI | 150 | 0.00855 | RISING MAINS |
| 3 | DI | 200 | 0.0059 | RISING MAINS |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 4.11 | DISTRIBUTION |
| 2 | HDPE | 63 | 3.48 | DISTRIBUTION |
| 3 | HDPE | 110 | 0.159 | DISTRIBUTION |
| 4 | HDPE | 140 | 0.476 | DISTRIBUTION |
| 5 | HDPE | 160 | 0.495 | DISTRIBUTION |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 740 |