Project Completion Certificate (Ground Water)
Scheme ID: 20067626 Name of Scheme: BIRPUR GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 5
Total Population Covered: 3049 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 16-Aug-2024 Actual Date of Completion (Capex): 03-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 27.01/136.30 BIRPUR 26.9368825 79.4572031
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 650/65 BIRPUR 26.9368825 79.4572031
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 175/18 BIRPUR 26.9368825 79.4572031
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.0275 RISING MAINS
2 DI 150 0.016 RISING MAINS
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 6.768 DISTRIBUTION
2 HDPE 63 6.195 DISTRIBUTION
3 HDPE 110 0.547 DISTRIBUTION
4 HDPE 140 1.124 DISTRIBUTION
5 HDPE 160 1.301 DISTRIBUTION
HSC Connection
Sno. Total Nos.
1 478
Other Details
3.64
3.62
3.64
07-Aug-2024
08-Aug-2024