| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20067683 | Name of Scheme: Nikarozpur | No. of Villages: 3 | No. of Habitation Covered: 9 |
| Total Population Covered: 2878 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2052 |
| Date of Completion (As per Contract): 26-Jul-2024 | Actual Date of Completion (Capex): 26-Jul-2026 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tube well -300X150 | 09/55.19 | Nikarozpur | 25.758615 | 82.597437 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Pump-15HP | 600/51.60 | Nikarozpur | 25.758615 | 82.597437 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 175KL-16M | Nikarozpur | 25.75849 | 82.59758 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 150 | 0.017 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE PN-6 | 160 | 0.038 | |
| 2 | HDPE PIPE PN-6 | 140 | 0.406 | |
| 3 | HDPE PIPE PN-6 | 110 | 0.903 | |
| 4 | HDPE PIPE PN-6 | 90 | 1.577 | |
| 5 | HDPE PIPE PN-6 | 63 | 10.127 | |
| 6 | HDPE PIPE PN-6 | 75 | 1.917 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 436 |