Project Completion Certificate (Ground Water)
Scheme ID: 20067853 Name of Scheme: NASIBPUR water supply scheme No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 2060 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 06-Jul-2023 Actual Date of Completion (Capex): 19-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tube Well 30.10 / 125.28 nasibpur 29.287679 78.419946
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump 450/ 50 nasibpur 29.287679 78.419946
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 125 / 14 nasibpur 29.287679 78.419946
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI - K7 100 0.025
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 6.1714
2 HDPE 75 0.5333
3 HDPE 90 0.4
HSC Connection
Sno. Total Nos.
1 328
Other Details
2.02
0.00
2.03
19-Nov-2025
20-Nov-2025