Project Completion Certificate (Ground Water)
Scheme ID: 20068069 Name of Scheme: ALEALIPUR WATER SUPPLY SCHEME No. of Villages: 3 No. of Habitation Covered: 3
Total Population Covered: 2180 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 23-Jan-2023 Actual Date of Completion (Capex): 16-May-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE PN -6: CLASS PE -100 63 3.92
2 HDPE PIPE PN -6: CLASS PE -100 75 0.51
3 HDPE PIPE PN -6: CLASS PE -100 90 0.21
4 HDPE PIPE PN -6: CLASS PE -100 110 0.80
HSC Connection
Sno. Total Nos.
Other Details
1.70
1.70
1.70
16-May-2025
17-May-2025