| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20068083 | Name of Scheme: TARA PUR WATER SUPPLY SCHEME | No. of Villages: 2 | No. of Habitation Covered: 5 |
| Total Population Covered: 1719 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 29-Apr-2024 | Actual Date of Completion (Capex): 07-Nov-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 12/62.5 | TARA PUR | 29.201362 | 77.727027 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 400/52 | TARA PUR | 29.201362 | 77.727027 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 100/14 | TARA PUR | 29.201362 | 77.727027 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI K-7 | 100 | 30 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 2.80 | |
| 2 | HDPE | 90 | 2.50 | |
| 3 | HDPE | 110 | 0.37 | |
| 4 | HDPE | 125 | 0.64 | |
| 5 | HDPE | 160 | 0.79 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |