Project Completion Certificate (Ground Water)
Scheme ID: 20068335 Name of Scheme: GARTHOLIYA & LOHANG PUR WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 13
Total Population Covered: 4186 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 08-Feb-2024 Actual Date of Completion (Capex): 06-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 29.17 M / 60.69 M GARTHOLIYA & LOHANG PUR 26.255608 81.799236
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 880 LPM / 56 M GARTHOLIYA & LOHANG PUR 26.255608 81.799236
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 250 KL / 18 M GARTHOLIYA & LOHANG PUR 26.255608 81.799236
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0265
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 24.904
2 HDPE 90 2.514
3 HDPE 110 0.845
4 HDPE 125 1.318
5 HDPE 160 1.439
6 HDPE 180 0.612
7 HDPE 200 1.750
HSC Connection
Sno. Total Nos.
1 994
Other Details
5.35
0.00
5.33
06-Sep-2024
07-Dec-2024