Project Completion Certificate (Ground Water)
Scheme ID: 20068337 Name of Scheme: NARI KHERA GOGP JJM No. of Villages: 3 No. of Habitation Covered: 4
Total Population Covered: 5470 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 22-Sep-2024 Actual Date of Completion (Capex): 28-Nov-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 36 m/108 m NARI KHERA 27.714865 80.197578
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 1160 LPM/47 M NARI KHERA 27.714865 80.197578
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 350 KL/18 M NARI KHERA 27.714865 80.197578
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 200 .033
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.021
2 HDPE 75 2.746
3 HDPE 90 3.328
4 HDPE 110 .806
5 HDPE 125 .356
6 HDPE 160 .139
7 HDPE 180 .116
8 HDPE 200 2.906
HSC Connection
Sno. Total Nos.
1 884
Other Details
3.62
0.00
3.68
27-Feb-2025
26-Sep-2025