Project Completion Certificate (Ground Water)
Scheme ID: 20068993 Name of Scheme: KAUL & TIGRI No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 5344 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 25-May-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 42.1 Mtr / 102.49 Mtr KAUL 29.154828 77.913395
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible 1000 LPM / 54 Mtr KAUL 29.154828 77.913395
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 300 Kl / 16 M KAUL 29.154828 77.913395
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 0.0248 Laying work done in Kaul Only
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 4.679 This is a multi-village scheme comprising two villages, Kaul and Tigri. The work has been completed in Kaul, but in Tigri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
2 HDPE 90 1.370 This is a multi-village scheme comprising two villages, Kaul and Tigri. The work has been completed in Kaul, but in Tigri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
3 HDPE 110 0.345 This is a multi-village scheme comprising two villages, Kaul and Tigri. The work has been completed in Kaul, but in Tigri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
4 HDPE 140 0.631 This is a multi-village scheme comprising two villages, Kaul and Tigri. The work has been completed in Kaul, but in Tigri, no work could be initiated due to villagers dispute. Hence, partial O&M has been started.
HSC Connection
Sno. Total Nos.
Other Details
4.46
4.46
2.73
11-Oct-2024
12-Oct-2024