| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20069024 | Name of Scheme: NAIDU & NAGLA KATAR | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 4526 | Base Year: 2022 | Intermediate Year: 2038 | Design Year: 2052 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 11-Mar-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 42.14 Mtr / 101.95 Mtr | NAIDU-NAGLA KATAR | 29.193115 | 77.84495 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersible | 900 LPM / 56 Mtr | NAIDU-NAGLA KATAR | 29.193115 | 77.84495 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 275 Kl/ 18 | NAIDU-NAGLA KATAR | 29.193115 | 77.84495 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 0.0223 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 5.056 | |
| 2 | HDPE | 90 | 2.540 | |
| 3 | HDPE | 110 | 0.409 | |
| 4 | HDPE | 125 | 0.173 | |
| 5 | HDPE | 140 | 0.172 | |
| 6 | HDPE | 160 | 0.177 | |
| 7 | HDPE | 200 | 1.762 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 801 |