Project Completion Certificate (Ground Water)
Scheme ID: 20069822 Name of Scheme: KASAIPUR WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 3020 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 05-Feb-2024 Actual Date of Completion (Capex): 28-Dec-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 19/68 Kasaipur 26.046921 82.329835
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 VT Pump-1 640LPM/48M Kasaipur 26.046921 82.329835
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 175KL/16M Kasaipur 26.046854 82.329997
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI Pipe K-7 100 0.04
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE-PN-6 , PE-100 63 16.393
2 HDPE-PN-6 , PE-100 75 2.121
3 HDPE-PN-6 , PE-100 90 1.269
4 HDPE-PN-6 , PE-100 110 1.043
5 HDPE-PN-6 , PE-100 140 1.002
6 HDPE-PN-6 , PE-100 160 0.032
7 HDPE-PN-6 , PE-100 200 0.02
HSC Connection
Sno. Total Nos.
Other Details
2.75
2.74
2.68
01-Apr-2025
02-Apr-2025