Project Completion Certificate (Ground Water)
Scheme ID: 20070405 Name of Scheme: Rasoolpur Sarai W/S Scheme No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 2270 Base Year: 2022 Intermediate Year: 2032 Design Year: 2052
Date of Completion (As per Contract): 31-Dec-2024 Actual Date of Completion (Capex): 10-Jan-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 24.03 Mtr/ 96.22 M Rasoolpur Sarai 28.593748 79.53501
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 10 HP Submersible Pump 32.4 cum / 44 M Rasoolpur Sarai 28.593748 79.53501
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 Conventional OHT 150KL/12M Rasoolpur Sarai 28.593748 79.53501
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 0.0579
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 63 3.0005
2 HDPE Pipe PN-6: Class PE-100 110 .246
3 HDPE Pipe PN-6: Class PE-100 140 0.088
4 HDPE Pipe PN-6: Class PE-100 160 .498
5 HDPE Pipe PN-6: Class PE-100 90 0.033
6 HDPE Pipe PN-6: Class PE-100 75 0.3711
HSC Connection
Sno. Total Nos.
1 454
Other Details
1.78
1.74
1.74
10-Apr-2024
11-Apr-2024