| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20070858 | Name of Scheme: KANOO WATER SUPPLY SCHEME | No. of Villages: 1 | No. of Habitation Covered: 14 |
| Total Population Covered: 2176 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 07-Feb-2024 | Actual Date of Completion (Capex): 24-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | TUBEWELL | 18 / 68.32 | KANOO | 26.061577 | 81.838093 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 500 LPM / 50 M | KANOO | 81.838093 | 26.061577 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT | 125 / 12 | KANOO | 81.838093 | 26.061577 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 100 | 0.0226 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 63 | 3.811 | |
| 2 | HDPE | 90 | 5.098 | |
| 3 | HDPE | 110 | 2.047 | |
| 4 | HDPE | 125 | 0.293 | |
| 5 | HDPE | 140 | 0.368 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 308 |