Project Completion Certificate (Ground Water)
Scheme ID: 20070874 Name of Scheme: BHIMI WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 15
Total Population Covered: 6040 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 08-Feb-2024 Actual Date of Completion (Capex): 24-Jun-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 1 16/95.5 BHIMI 26.1777685 81.905035
2 TUBEWELL 2 19/97.3 BHIMI 26.178050 81.907916
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 1 625 LPM / 54 M BHIMI 26.1777685 81.905035
2 SUBMERSIBLE 2 625 LPM / 54 M BHIMI 26.178050 81.907916
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 375 KL / 16 BHIMI 26.1777685 81.905035
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 100 0.39
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 63 16.372
2 HDPE 90 5.228
3 HDPE 110 1.635
4 HDPE 140 1.399
5 HDPE 200 0.837
HSC Connection
Sno. Total Nos.
1 1159
Other Details
6.35
0.00
6.22
24-Sep-2024
25-Dec-2024