| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20072514 | Name of Scheme: SUBARPUR WSS | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 2180 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 15-Mar-2024 | Actual Date of Completion (Capex): 30-Apr-2025 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Lowering of tubewell assembly | 18/117.32 | Subarpur | 26.374882 | 82.61673 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | ACsubmersible pumping 12.5HP | 460Lpm /43 | Subarpur | 26.374882 | 82.61673 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | RCC | 125kl/12 | Subarpur | 26.374882 | 82.61673 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI-K7 | 100 | 0.032 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE Pipe PN-6: Class PE-100 | 90 | 2.09 | |
| 2 | HDPE Pipe PN-6: Class PE-100 | 75 | 1.628 | |
| 3 | HDPE Pipe PN-6: Class PE-100 | 63 | 4.817 | |
| 4 | HDPE Pipe PN-6: Class PE-100 | 110 | 0.260 | |
| 5 | HDPE Pipe PN-6: Class PE-100 | 140 | 0.529 | |
| 6 | HDPE Pipe PN-6: Class PE-100 | 160 | 1.270 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 340 |