Project Completion Certificate (Ground Water)
Scheme ID: 20072514 Name of Scheme: SUBARPUR WSS No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 2180 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 15-Mar-2024 Actual Date of Completion (Capex): 30-Apr-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Lowering of tubewell assembly 18/117.32 Subarpur 26.374882 82.61673
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 ACsubmersible pumping 12.5HP 460Lpm /43 Subarpur 26.374882 82.61673
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 RCC 125kl/12 Subarpur 26.374882 82.61673
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI-K7 100 0.032
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE Pipe PN-6: Class PE-100 90 2.09
2 HDPE Pipe PN-6: Class PE-100 75 1.628
3 HDPE Pipe PN-6: Class PE-100 63 4.817
4 HDPE Pipe PN-6: Class PE-100 110 0.260
5 HDPE Pipe PN-6: Class PE-100 140 0.529
6 HDPE Pipe PN-6: Class PE-100 160 1.270
HSC Connection
Sno. Total Nos.
1 340
Other Details
2.00
1.87
1.87
30-Apr-2025
01-May-2025