| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20072604 | Name of Scheme: JEEVPUR MUSTKAM MVS (O) | No. of Villages: 2 | No. of Habitation Covered: 2 |
| Total Population Covered: 2037 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 31-Dec-2024 | Actual Date of Completion (Capex): 16-Sep-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 18.19/101.08 | Jeevpur Mustahkam | 28.462029 | 78.315052 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Solar Powered Pump | 434/44 | Jeevpur Mustahkam | 28.462029 | 78.315052 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | Cast in situ Zinc Zincalume | 125/12 | Jeevpur Mustahkam | 28.456367 | 78.32228 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | K-7/DI | 100 | 0.030 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | PN-6 PE100/HDPE | 63 | 3.6534 | |
| 2 | PN-6 PE100/HDPE | 75 | 0.484 | |
| 3 | PN-6 PE100/HDPE | 90 | 0.056 | |
| 4 | PN-6 PE100/HDPE | 110 | 0.2549 | |
| 5 | PN-6 PE100/HDPE | 125 | 0.9182 | |
| 6 | PN-6 PE100/HDPE | 140 | 0.6008 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 297 |