Project Completion Certificate (Ground Water)
Scheme ID: 20072882 Name of Scheme: Saraiyya Mohan GP water supply scheme No. of Villages: 2 No. of Habitation Covered: 5
Total Population Covered: 3270 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 03-Nov-2024 Actual Date of Completion (Capex): 06-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 150 MM PLAIN PIPE 4 SARAIYA MOHAN 26.174484 81.935730
2 200 MM PLAIN PIPE 47.50 SARAIYA MOHAN 26.174484 81.935730
3 200 MM SLOTTED PIPE 20 SARAIYA MOHAN 26.174484 81.935730
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 550LPM/53Mtr SARAIYA MOHAN 26.174484 81.935730
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 100 KL / 12MTR SARAIYA MOHAN 26.174484 81.935730
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 100 0.02590
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 4.07
2 HDPE 63 8.82
3 HDPE 110 3.33
4 HDPE 140 2.14
5 HDPE 160 0.425
HSC Connection
Sno. Total Nos.
1 391
Other Details
3.03
0.00
2.89
10-Dec-2024
12-Dec-2024