Project Completion Certificate (Ground Water)
Scheme ID: 20073006 Name of Scheme: KATEHATI WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 8
Total Population Covered: 3189 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 14-Mar-2025 Actual Date of Completion (Capex): 07-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 300MM PLAIN PIPE 44 KATEHATI 26.47052 81.67983
2 150MM PLAIN PIPE 31.3 KATEHATI 26.47052 81.67983
3 300MM SLOTTED PIPE 12 KATEHATI 26.47052 81.67983
4 150MM SLOTTED PIPE 7 KATEHATI 26.47052 81.67983
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 700LPM / 56MTR KATEHATI 26.47052 81.67983
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OVER HEAD TANK 200KL / 18MTR KATEHATI 26.47052 81.67983
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 .054
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 5.979
2 HDPE PIPE 63 9.061
3 HDPE PIPE 110 1.223
4 HDPE PIPE 125 .343
5 HDPE PIPE 140 .869
HSC Connection
Sno. Total Nos.
1 640
Other Details
3.35
0.00
3.26
12-Dec-2024
15-Mar-2025