Project Completion Certificate (Ground Water)
Scheme ID: 20075940 Name of Scheme: SUWAHERI KHURD WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 1
Total Population Covered: 1890 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 22-Dec-2023 Actual Date of Completion (Capex): 23-Dec-2022
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 3.17 HDPE PIPE
2 HDPE PIPE 75 0.02 HDPE PIPE
3 HDPE PIPE 90 0.08 HDPE PIPE
4 HDPE PIPE 110 0.08 HDPE PIPE
5 HDPE PIPE 125 0.12 HDPE PIPE
HSC Connection
Sno. Total Nos.
Other Details
1.64
1.64
1.51
15-Nov-2024
16-Nov-2024