Project Completion Certificate (Ground Water)
Scheme ID: 20076517 Name of Scheme: TIKARI WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 15
Total Population Covered: 10571 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 25-Mar-2025 Actual Date of Completion (Capex): 06-Sep-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 150 MMØ PLAIN PIPE 30.8 TIKRI 26.204637 81.865407
2 300 MMØ PLAIN PIPE 117.00 TIKRI 26.204637 81.865407
3 150 MMØ SLOTTED PIPE 10 TIKRI 26.204637 81.865407
4 300 MMØ SLOTTED PIPE 52.00 TIKRI 26.204637 81.865407
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUMMERSIBLE PUMP 880 LPM/56 M TIKRI 26.204637 81.865407
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 500 KL / 18 M TIKRI 26.204637 81.865407
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 150 1.043
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 90 1.546
2 HDPE PIPE 75 1.753
3 HDPE PIPE 63 26.755
4 HDPE PIPE 110 3.006
5 HDPE PIPE 140 1.051
6 HDPE PIPE 160 0.728
7 HDPE PIPE 200 1.762
HSC Connection
Sno. Total Nos.
1 1772
Other Details
9.98
0.00
9.62
04-Dec-2024
12-Mar-2025