Project Completion Certificate (Ground Water)
Scheme ID: 20076525 Name of Scheme: PHOOLA WATER SUPPLY SCHEME No. of Villages: 1 No. of Habitation Covered: 26
Total Population Covered: 8816 Base Year: 2022 Intermediate Year: 2037 Design Year: 2052
Date of Completion (As per Contract): 15-Sep-2024 Actual Date of Completion (Capex): 03-Jul-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 150 MM PLAIN PIPE 6 PHOOLA 26.439065 81.473812
2 300 MM PLAIN PIPE 113.5 PHOOLA 26.439065 81.473812
3 300 MM SLOTTED PIPE 35 PHOOLA 26.439065 81.473812
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE PUMP 885 LPM/ 55 M PHOOLA 26.439065 81.473812
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 500 KL / 17 M PHOOLA 26.439065 81.473812
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI PIPE 150 0.8895
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 31.528
2 HDPE PIPE 75 2.562
3 HDPE PIPE 90 2.250
4 HDPE PIPE 110 1.467
5 HDPE PIPE 125 0.884
6 HDPE PIPE 140 0.347
7 HDPE PIPE 180 1.027
8 HDPE PIPE 200 0.537
9 DI PIPE 200 1.362
10 DI PIPE 250 3.257
11 DI PIPE 300 0.503
HSC Connection
Sno. Total Nos.
1 1802
Other Details
8.93
0.00
8.91
02-Oct-2024
15-Jan-2025