| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20076887 | Name of Scheme: KURELI SVS | No. of Villages: 1 | No. of Habitation Covered: 3 |
| Total Population Covered: 3200 | Base Year: 2023 | Intermediate Year: 2038 | Design Year: 2053 |
| Date of Completion (As per Contract): 30-May-2025 | Actual Date of Completion (Capex): 18-Jan-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | Tubewell | 30M/101m | KURELI | 27.34619 | 79.50059 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | Submersibel Pump | 700LPM/61M | KURELI | 27.34619 | 79.50059 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OHT-1 | 200KL/14M | KURELI | 27.34619 | 79.50059 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI | 150 | 14.80 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE | 90 | 2.418 | |
| 2 | HDPE | 63 | 3.673 | |
| 3 | HDPE | 110 | 0.602 | |
| 4 | HDPE | 140 | 0.317 | |
| 5 | HDPE | 160 | 1.204 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 714 |