Project Completion Certificate (Ground Water)
Scheme ID: 20077071 Name of Scheme: PHARHAN GRAM PANCHAYAT WATER SUPPLY SCHEME No. of Villages: 2 No. of Habitation Covered: 2
Total Population Covered: 1774 Base Year: 2023 Intermediate Year: 2038 Design Year: 2053
Date of Completion (As per Contract): 16-Aug-2024 Actual Date of Completion (Capex): 21-Jan-2025
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 Tubewell 16.00/60.01 PHARHAN 79.76073 27.19667
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 Submersible Pump-1 400 LPM/56 M PHARHAN 79.76073 27.19667
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT-1 125 KL/ 14 M PHARHAN 79.76073 27.19667
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 80 0.0021 Rising main
2 DI 100 0.0152 Rising main
3 DI 150 0.0073 Rising main
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE 90 1.69 Distribution
2 HDPE 63 2.71 Distribution
3 HDPE 110 0.761 Distribution
HSC Connection
Sno. Total Nos.
1 353
Other Details
2.20
2.15
2.20
23-Apr-2025
24-Apr-2025