Project Completion Certificate (Ground Water)
Scheme ID: 20077631 Name of Scheme: GAHILAPUR No. of Villages: 1 No. of Habitation Covered: 3
Total Population Covered: 3127 Base Year: 2023 Intermediate Year: 2038 Design Year: 2023
Date of Completion (As per Contract): 20-Mar-2023 Actual Date of Completion (Capex): 22-Mar-2024
Tubewells
Sno. Description Depth of Strainer (m) / Depth of Plain Pipe (m) Location Latitude Longitude
1 TUBEWELL 24/224.57 Gahilapur 26.505312° 79.73863°
Pumps
Sno. Type of Pump Discharge (M³) / Head(Mtr.) Location Latitude Longitude
1 SUBMERSIBLE 650/68 Gahilapur 26.505312° 79.73863°
OHT's
Sno. Structure Capacity (In KL) / Staging Ht.(Mtr.) Location Latitude Longitude
1 OHT 200/12 Gahilapur 26.505312° 79.73863°
Clear Water Rising Main
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 DI 100 0.037
Distribution Network
Sno. Pipe Type / Material Dia (In mm.) Length (In KM.) Remarks
1 HDPE PIPE 63 5.083
2 HDPE PIPE 75 1.693
3 HDPE PIPE 90 0.711
4 HDPE PIPE 125 1.208
5 HDPE PIPE 140 0.013
6 HDPE PIPE 160 0.555
7 HDPE PIPE 180 0.025
HSC Connection
Sno. Total Nos.
1 657
Other Details
2.43
0.00
2.81
26-May-2025
27-May-2025