| Project Completion Certificate (Ground Water) | |||
|---|---|---|---|
| Scheme ID: 20077657 | Name of Scheme: Mayas & Nimi Water Supply Scheme | No. of Villages: 2 | No. of Habitation Covered: 10 |
| Total Population Covered: 4230 | Base Year: 2022 | Intermediate Year: 2037 | Design Year: 2057 |
| Date of Completion (As per Contract): 10-Aug-2024 | Actual Date of Completion (Capex): 27-Jun-2024 | ||
| Tubewells | |||||
|---|---|---|---|---|---|
| Sno. | Description | Depth of Strainer (m) / Depth of Plain Pipe (m) | Location | Latitude | Longitude |
| 1 | 300 PLAIN PIPE | 53 | MAYAS | 26.323612 | 81.71332 |
| 2 | 300 SLOTTED PIPE | 20.20 | MAYAS | 26.323612 | 81.71332 |
| 3 | 150 PLAIN PIPE | 22.30 | MAYAS | 26.323612 | 81.71332 |
| 4 | 150 SLOTTED PIPE | 8 | MAYAS | 26.323612 | 81.71332 |
| Pumps | |||||
|---|---|---|---|---|---|
| Sno. | Type of Pump | Discharge (M³) / Head(Mtr.) | Location | Latitude | Longitude |
| 1 | SUBMERSIBLE | 890LPM / 54MTR | MAYAS | 26.323612 | 81.71332 |
| OHT's | |||||
|---|---|---|---|---|---|
| Sno. | Structure | Capacity (In KL) / Staging Ht.(Mtr.) | Location | Latitude | Longitude |
| 1 | OVER HEAD TANK | 275KL/16MTR | MAYAS | 26.323612 | 81.71332 |
| Clear Water Rising Main | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | DI PIPE | 150 | .027 | |
| Distribution Network | ||||
|---|---|---|---|---|
| Sno. | Pipe Type / Material | Dia (In mm.) | Length (In KM.) | Remarks |
| 1 | HDPE PIPE | 90 | 5.84 | |
| 2 | HDPE PIPE | 63 | 13.90 | |
| 3 | HDPE PIPE | 110 | 3.64 | |
| 4 | HDPE PIPE | 140 | .909 | |
| 5 | HDPE PIPE | 200 | 2.77 | |
| HSC Connection | |
|---|---|
| Sno. | Total Nos. |
| 1 | 800 |